更多“78 The process of choosing/documenting the best approach to achieve the project objectives is part of: A. The scope baseline.B. Scope authorizationC. Scope definitionD. Scope planning.E. All of the above.”相关问题
  • 第1题:

    The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A.The scope baseline.

    B.Scope authorization

    C.Scope definition

    D.Scope planning.

    E.All of the above.


    正确答案:D
    D

  • 第2题:

    140 In which of the following scope management processes are subject matter experts used? A. Initiation

    B. Scope planning

    C. Scope Definition

    D. Scope change control

    E. Scope verification


    正确答案:A

  • 第3题:

    142 The project charter is prepared in which scope management process?

    A. Initiation

    B. Scope planning

    C. Scope Definition

    D. Scope change control

    E. Scope verification


    正确答案:A

  • 第4题:

    144 Which of the following is not a scope management process?

    A. Initiation

    B. Scope planning

    C. Scope Definition

    D. Scope change control

    E. Scope verification


    正确答案:D

  • 第5题:

    160 The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A. The scope baseline.

    B. Scope authorization

    C. Scope definition

    D. Scope planning.

    E. All of the above


    正确答案:D

  • 第6题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第7题:

    ● The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A The scope baseline.

    B Scope authorization

    C Scope definition

    D Scope planning.

    E All of the above.


    正确答案:D

  • 第8题:

    ( ) describes, in detail, the project’ s deliverables and the work required to create those deliverables.

    A.Product scope description B.Project objectives C.Product specification D.The project scope statement


    正确答案:D

  • 第9题:

    ● Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components? (74)

    (74)

    A. Scope Planning

    B. Scope Verification

    C. Scope Change Control

    D. Scope Definition


    正确答案:D

  • 第10题:

    () is the process of obtaining the stakeholders\' formal acceptance of thecompleted project scope. Verifying the scope includes reviewing deliverables and work results toensure that all were completed satisfactorily.

    A.Project acceptance
    B.Scope verification
    C.Scope definition
    D.WBS Creation

    答案:B
    解析:
    范围验证是指获得项目干系人对已完成的项目范围的正式认可的过程。验证范围包括了评审可交付物和工作成果,以确定它们均已令人满意地完成。

  • 第11题:

    () is the process of obtaining the stakeholders' formal acceptance of the completed project scope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A、projectacceptance
    • B、scopeverification
    • C、scopedefinition
    • D、WBS Creation

    正确答案:B

  • 第12题:

    单选题
    ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.
    A

    Project acceptance

    B

    Scope verification

    C

    Scope definition

    D

    WBS Creation


    正确答案: D
    解析: 范围验证是指获取项目干系人对已完成的项目范围的正式认可的过程。验证范围包括评审可交付物和工作成果,以确保这些工作都已按照范围定义中的要求完成。

  • 第13题:

    120 The Work Breakdown Structure (WBS) is the basis for communicating:

    A. Project scope, cost control, schedule, quality

    B. Project objectives, dependencies, plan, cost control

    C. Project scope, schedule, staffing, cost control

    D. Project scope, quality, schedule, dependencies

    E. Project budget, schedule, risk factors, work assignments


    正确答案:A

  • 第14题:

    141 The work breakdown structure (WBS) is first developed in which scope management process? A. Initiation

    B. Scope planning

    C. Scope change control

    D. Scope Definition

    E. Scope verification


    正确答案:D

  • 第15题:

    143 In which of the following scope management processes is the scope management plan prepared?

    A. Initiation

    B. Scope planning

    C. Scope Definition

    D. Scope change control

    E. Scope verification


    正确答案:B

  • 第16题:

    146 Which of the following are included as part of a scope statement?

    A. Project justification

    B. Project deliverables

    C. Project objectives

    D. All of the above

    E. B and C


    正确答案:D

  • 第17题:

    ● Which of the following are included as part of a scope statement?

    A Project justification

    B Project deliverables

    C Project objectives

    D All of the above

    E B and C


    正确答案:D

  • 第18题:

    ● Scope management is:

    A a project control function.

    B employs change control.

    C a work authorization process.

    D considers Cost, Quality and Schedule.

    E All of the above.


    正确答案:E

  • 第19题:

    is the process of obtaining the stakeholdrs'formal acceptance of the completed project scope. Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.WBS Creation

    B.Scope definition

    C.Project acceptance

    D.Scope verification


    正确答案:D

  • 第20题:

    The( )is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A、project scope statement

    B、work package

    C、WBS

    D、project scope plan


    参考答案:C

  • 第21题:

    ( ) describes,in detail,the project’s deliverables and the work required to create those deliverables.

    A.Product scope description
    B.Project objectives
    C.Stakeholder Analysis
    D.The project scope statement

    答案:D
    解析:
    项目范围说明书详细描述项目的可交付成果和为了提交这些可交付成果而必须开展的工作。(72) A.产品范围说明书 B.项目目标 C.干系人分析 D.项目范围说明说

  • 第22题:

    The()is a hierarchical decomposition of the total scope of work to be Carried out by the project team to accomplish the project objectives and create the required deliverables.

    A.Project scope statement
    B.Work package
    C.WBS
    D.Project scope plan

    答案:C
    解析:
    ()是项目团队为完成项目目标和创建所需可交付成果而执行的整个工作范围的分层分解。
    A.项目范围说明书B.工作包C.WBS?D.项目范围计划

  • 第23题:

    ()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    • A、Project acceptance
    • B、Scope verification
    • C、Scope definition
    • D、WBS Creation

    正确答案:B