Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A.All activities.B.Only those activities with the longest time duration

题目

Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

A.All activities.

B.Only those activities with the longest time durations.

C.Those activities on the critical path begining with the longest time duration activities.

D.Those activities with the greatest degree of risk.

E.None of the above.


相似考题
更多“Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:A.All activities.B.Only those activities with the longest time duration”相关问题
  • 第1题:

    The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form. does the project manager probably have the easiest time in integrating work?

    A . Matrix

    B . Classical

    C . Expediter

    D . Coordinator

    E . Pure project


    正确答案:E

  • 第2题:

    163 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:

    A. The project will be completed late.

    B. The critical path has been lengthened.

    C. the costs are being overrun.

    D. Overtime will be required to maintain the original critical path.

    E. None of the above.


    正确答案:E

  • 第3题:

    ● Free float is the amount of time that an activity may be delayed with out affecting the _____.

    A Early start of the succeeding activities.

    B Late start of the succeeding activities.

    C Project finish.

    D Cost of the project.

    E None of the above.


    正确答案:A

  • 第4题:

    ● Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

    A All activities.

    B Only those activities with the longest time durations.

    C Those activities on the critical path begining with the longest time duration activities.

    D Those activities with the greatest degree of risk.

    E None of the above.


    正确答案:C

  • 第5题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。 A.project management plan B.project charter C.project human resource plan D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第6题:

    In project management,a ( ) is a list of a project’s milestones,activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.

    A.schedule

    B.WBS

    C.SOW

    D.charter


    正确答案:A
    在项目管理中,进度管理的里程碑清单、活动和可交付物,通常都有明确的开始和结束日期,这些条目通常在资源分配中已经进行估算,在预算和持续时间上依赖于事件的调度。

  • 第7题:

    In project management , a (1) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (2) ,budget and duration, linked by dependencies and scheduled events.

    A.schedule

    B.activity

    C.plan

    D.contractor@@@SXB@@@A.finding

    B.balance

    C.allocation

    D.distribution


    正确答案:A,C

  • 第8题:

    In order to facilitate configuration and change management, manual or automated tools maybe used. Tools selection should be based on the needs of the( ).

    A. Project manager
    B.CCB.members
    C.Project stakeholders
    D. Project Management Office(PMO)

    答案:C
    解析:
    翻译:为了便于实施配置和变更管理,会使用到一些手工或者自动工具,工具的选择取决于项目干系人的需要。A.项目经理 B.变更委员会成员 C.项目干系人 D.项目管理办公室

  • 第9题:

    Project Integration Management includes the processes and activities to identify,define,combine,unify,and coordinate the various processes and project management activities within the Project Management Process Groups.( )process does not belong to Project Integration Management.

    A.Developing project charter
    B.Developing project management plan
    C.Analyzing project risks
    D.Monitoring and controlling project

    答案:C
    解析:
    项目整合管理包括在项目管理过程组中识别、定义、组合、统一和协调各种过程和项目管理活动的过程和活动。识别项目风险过程不属于项目整合管理。
    A制定项目章程,B制定项目管理计划,C识别项目风险,D指导与管理项目。

  • 第10题:

    In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.

    • A、schedule
    • B、activity
    • C、plan
    • D、contractor

    正确答案:A

  • 第11题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、projectcharter

    正确答案:D

  • 第12题:

    单选题
    The()provides the project manager with the authority to apply organizational resources to project activities.
    A

    project management plan

    B

    contract

    C

    project human resource plan

    D

    project charter


    正确答案: A
    解析: 项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第13题:

    111 Management has decided to "crash" a project in order to avoid penalty payments for late deliveries. To crash the project, either overtime or additional resources should be assigned to:

    A. All activities.

    B. Only those activities with the longest time durations.

    C. Those activities on the critical path begining with the longest time duration activities.

    D. Those activities with the greatest degree of risk.

    E. None of the above


    正确答案:C

  • 第14题:

    112 Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

    A. P

    B. Q

    C. R

    D. S

    E. T


    正确答案:A

  • 第15题:

    ● Increasing resources on the critical path activities may not always shorten the length of the project because:

    A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake).

    B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project.

    C The skill level of the added resources might not be appropriate for the activities to be performed.

    D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.)

    E All of the above.


    正确答案:E

  • 第16题:

    The(70)provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.contract

    C.project human resource plan

    D.project charter


    正确答案:D
    解析:项目章程为项目经理使用组织资源进行项目活动提供了授权。

  • 第17题:

    The( )provides the project manager with the authority to apply organizational resources to project activities。

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B
    项目章程(project charter)为项目经理使用组织资源进行项目活动提供了授权。

  • 第18题:

    The (73) provides the project manager with the authority to apply organizational resources to project activities.

    A.project management plan

    B.project charter

    C.project human resource plan

    D.project stakeholders


    正确答案:B

  • 第19题:

    The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.

    A.Contingency reserve
    B.Project profit
    C.Management reserve
    D.Special fund

    答案:C
    解析:
    项目的预算还未最终确定,额外的工作已经发现,没有计划的预算或并不在项目范围内。管理储备可以提供该基金支付新发现的工作项。

  • 第20题:

    In project time management processes, ( )involves identifying and documenting the relationships between project activities.

    A.activity definition
    B.activity sequencing
    C.schedule control
    D.schedule development

    答案:B
    解析:
    解析:翻译:在项目进度管理中,( )用于确定和记录各个活动任务之间的关联关系。A.活动定义B..活动排序C.进度控制D.进度计划

  • 第21题:

    A project is a[temporary](请作答此空)of unique,complex,and connected activities having one goal or purpose and that must be completed by a specific time,within budget,and according to( ).Project management is the process of scoping,planning,staffing,organizing,directing,and controlling the development of a(n)( )system at a minimum cost within a specified time frame.For any systems development project,effective project management is necessary to ensure that the project meets the( ),is developed within an acceptable budget,and fulfills customer expectations and specifications,Project management is a process that starts at the beginning of a project,extends through a project,and doesn't culminate until the project is completed.The prerequisite for good project management is a well-defined system development process.Process management is an ongoing activity that documents,manages the use of,and improves an organization s chosen methodology(the“process”)for system development,Process management is concerned with the activities,deliverables,and quality standards to be applied to( )project(s).

    A.task
    B.work
    C.sequence
    D.activity

    答案:C
    解析:
    表示序列的意思。
    附(参考翻译):一个项目是一个独特的、复杂的、相互关联的活动的[临时]序列,有一个目标或目的,必须在特定的时间、预算内和根据规范完成。项目管理是一个范围界定、计划、人员配置、组织、指导和控制可接受系统开发的过程,在规定的时间内以最低的成本进行。对于任何系统开发项目,有效的项目管理都是必要的,以确保项目在截止日期前完成,在可接受的预算内开发,并满足客户的期望和规范,项目管理是从项目开始时开始的过程,延伸到一个项目中,直到项目完成才达到顶点。良好的项目管理的先决条件是定义良好的系统开发过程。过程管理是一项持续的活动,它记录、管理和改进组织为系统开发所选择的方法(“过程”),过程管理涉及应用于所有项目的活动、可交付成果和质量标准。

  • 第22题:

    The()provides the project manager with the authority to apply organizational resources to project activities.

    • A、project management plan
    • B、contract
    • C、project human resource plan
    • D、project charter

    正确答案:D

  • 第23题:

    单选题
    The()provides the project manager with the authority to apply organizational resources to project activities.
    A

    project management plan

    B

    contract

    C

    project human resource plan

    D

    projectcharter


    正确答案: D
    解析: 该题的关键词为"authority to apply organizational resources",其语句结构为"The____(主语)provides(谓语)the project manager with the authority to apply organizationalresources",含义为"什么为项目经理提供了使用组织资源的权力",根据项目管理知识,为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。